CONTACT APPLICANT | 5/3/2019 | JEFF LYALL | (5/3/2019 7:53:54 AM JLY) Action Created
(5/3/2019 7:53 AM JLY)
CALLED TIM TO ADVISE SUBDIV PHASE 3, 4, 5, 6, AND THE BUILDOUT PHASWE ARE APPROVED BY ALL DEPTS - ENG PENDING PAD CERT AND COMPACTION REPORT, PLANNING REVIEW PENDING |
More Info
|
MISCELLANEOUS | 4/10/2019 | JEFF LYALL | (4/10/2019 11:53:47 AM JLY) Action Created
(4/10/2019 11:53 AM JLY)
WHEN TIM SUBMITS 6TH SET, RT TO TRAFFIC FOR PH 3 |
More Info
|
PLANS ROUTED | 3/11/2019 | PAULA WEIGAND | (3/13/2019 7:43:03 AM PWE) Action Created
(3/13/2019 7:43 AM PWE)
TIM HAD HIS RUNNER BRING IN NEW SETS FOR PHASE 2 BLDGS 5 & 6. HE NEEDED MORE SETS SO WAS NOT ROUTED TILL TODAY. ROUTED: CITY & OWNER= BLDG // APN = RICHARD//FIRE=ANNE // TRANSPORTATION=TEALA// ENG=PAUL //WATER=IBRAHIM. I FOLLOWED THE PHASE ONE ROUTING AND FEES. |
More Info
|
PLANS RECEIVED | 3/6/2019 | PAULA WEIGAND | (3/6/2019 1:09:35 PM PWE) Action Created
(3/6/2019 1:09 PM PWE)
THESE PLANS WERE ORIGINALLY GIVEN TO JEFF BUT NEEDED REV SLIPS WHICH JEFF REQUESTED. TODAY 3 REVISION FORMS WERE BROUGHT IN ALSO 5 SETS OF PLANS FOR THE REV FOR BLDG # 4&7 [BOTH THESE BLDG ON ONE SET OF PLANS] AND 5 SETS OF PLANS FOR REV FOR BLDG #3 -EACH 'SET' IS ONE PAGE. POER DOUG ROUTE TO PLANNING/BLDG AND ENG. ROUTED: ENG REV = PAUL P // PLANNING REV= RICHARD // CITY REV, OWNER REV AND APN REV= DOUG.COPIES OF REV SHEETS TO PLANNING AND ENG- ORIGINAL REV SHEETS TO DOUG ON PLANS. PRICING ON EACH BLDG PERMIT SEPERATELY-INVOICES IN FILE FOLDER-NOT PAID YET. |
More Info
|
PLANS RECEIVED | 3/5/2019 | JEFF LYALL | (3/5/2019 11:45:36 AM JLY) Action Created
(3/5/2019 11:45 AM JLY)
ALEX RESUBMITTED 2 SLIP SHEETED SETS, CITY AND OWNER 6 - FOR MODEL PHASE BLDG3 |
More Info
|
CONTACT APPLICANT | 3/4/2019 | JEFF LYALL | (3/4/2019 2:55:47 PM JLY) Action Created
(3/4/2019 2:55 PM JLY)
called tim lm advising bldg approved model phase bldg 3, eng on hold and planning has corr |
More Info
|
PLANS RECEIVED | 2/22/2019 | PAULA WEIGAND | (2/22/2019 3:29:11 PM PWE) Action Created
(2/22/2019 3:29 PM PWE)
2 NEW MASTER SETS RESUBMITTED BY LIZ-PER DOUG ROUTE ONLY TO HIM. OWNER 5 AND CITY 5 TO DOUGS CUBBY WITH PACKIT OF COMMENT RESPONSES |
More Info
|
PLANS RECEIVED | 2/21/2019 | PAULA WEIGAND | (2/21/2019 3:58:15 PM PWE) Action Created
(2/21/2019 3:58 PM PWE)
LIZ RESUBMITTED 4 NEW SETS FOR : PHASE 1 BLDGS 4 &7 [ON ONE PLAN SET] AND PHASE 1 BLDG #3-PER DOUG ONLY NEEDS TO GO TO HIM -ALL TO DOUG |
More Info
|
PLANS RECEIVED | 2/11/2019 | ARTHUR CRONIN | (2/11/2019 3:00:58 PM ACR) Action Created
(2/11/2019 3:00 PM ACR)
APPLICANT SLIP SHEETED THIRD SUBMITTAL AND SUBMITTED PC RESPONSES. 3 SETS TOTAL. CITY, TRANSPORTATION AND APN |
More Info
|
CONTACT APPLICANT | 1/30/2019 | ARTHUR CRONIN | (1/30/2019 1:46:33 PM ACR) Action Created
(1/30/2019 1:46 PM ACR)
SPOKE WITH TIM ABOUT CORRECTIONS |
More Info
|
PLANS RECEIVED | 1/30/2019 | JEFF LYALL | (1/30/2019 10:07:34 AM JLY) Action Created
(1/30/2019 10:07 AM JLY)
TIM SUBMITTED 5 SETS OF PLANS FOR BLDGS 4 AND 7 - BOTH BUILDINGS ON 1 PLAN SET |
More Info
|
PLANS RECEIVED | 1/29/2019 | JEFF LYALL | (1/30/2019 10:16:34 AM JLY) Action Created
(1/30/2019 10:16 AM JLY)
TIM SUBMITTED 5 SETS OF PLANS FOR BLDG 3, (2) ROUGH PAD CERTS FOR BLDGS 1-16, (2) GEO REPORTS AND (2) SEQUENCE SHEETS |
More Info
|
PLANS RECEIVED | 1/22/2019 | ARTHUR CRONIN | (1/22/2019 12:04:41 PM ACR) Action Created
(1/22/2019 12:04 PM ACR)
5 SETS OF PLANS, 2 COPIES OF STRUCTRUAL CALCS, POST TENSION CALCS, T-24 REPORT, RESPONSES TO COMMENTS |
More Info
|
FILED PLANS | 12/31/2018 | PAULA WEIGAND | (12/31/2018 4:21:50 PM PWE) Action Created
(12/31/2018 4:21 PM PWE)
APN 2 SET RETURNED FROM TEALA |
More Info
|
PLANS ROUTED | 12/31/2018 | PAULA WEIGAND | (12/31/2018 4:21:19 PM PWE) Action Created
(12/31/2018 4:21 PM PWE)
TEALA ROUTED APN 2 FOR REVIEW AS SHE HAD NOT RECEIVED PLANS FROM AUGUST REVIEW SET |
More Info
|
PLANS ROUTED | 12/27/2018 | PAULA WEIGAND | (12/27/2018 9:52:47 AM PWE) Action Created
(12/27/2018 9:52 AM PWE)
EMAILED RG REGARDING PLANNING STATUS HE HAD NOT RECEIVED A SECOND SUBMITTAL REVIEW NOR PLANS-ROUTED THE CITY 2 SET TO HIM FOR REVIEW |
More Info
|
PLANS RECEIVED | 11/21/2018 | JONATHAN WELLS | (11/21/2018 8:38:13 AM JWE) Action Created
(11/21/2018 8:38 AM JWE)
(5) NEW SETS OF PLANS; WRITTEN RESPONSES TO CORR FOR (3) DEPTS; TITLE 24; GEOTECH LETTER; TRUSS LAYOUT AND CALCS, STRUC CALCS; POST TENSION CALCS; DOME DETAIL FOR REVIEW |
More Info
|
CONTACT APPLICANT | 8/29/2018 | ARTHUR CRONIN | (8/29/2018 2:26:26 PM ACR) Action Created
(8/29/2018 2:26 PM ACR)
LEFT A VOICEMAIL FOR TIM INFORMING OF REVIEW STATUS |
More Info
|
PLANS PICKED UP | 8/29/2018 | PAULA WEIGAND | (8/29/2018 3:21:04 PM PWE) Action Created
(8/29/2018 3:21 PM PWE)
ISIAH PU MASTER PLAN [ ONLY ENGINEERING SET] AND COMMENTS FROM WATER / ENG AND BLDG. |
More Info
|